Construction process

Name of construction: Polyfunkčná budova Trebišov - Juh
Place: Trebišov, p.č. 2012/5, 07501 Trebišov
Building Company: Oremus estate s.r.o., č. 53, Malá Bara 076 32, Logman a.s., Bratislava
Project Manager: Mars združenie projektová a inžinierska kancelária, Košice
Contractor: Weinberg'93 s.r.o.
Budova Oremus - Logman
Working-out of project:
08/2008
The date of construction beginning: 11/2008
The date of construction finishing: 06/2009
Opening date: 07/2009

Basic data
Obostavaný priestor: 12782 m3
Built Area: 1162 m2
Rooms Area: 2789 m2

The intent was to built a polyfunctional building, which is situated between the Street SNP and the Street MRŠ, at south part of the town. There were no alterations made to terrain under the building, as it is of flat character.
Výstavba objektu Oremus - Logman Výstavba objektu Oremus - Logman Výstavba objektu Oremus - Logman Výstavba objektu Oremus - Logman






The building does not have any influence on enviroment. During process of building-up, waste was carried out periodically. The same is for building today.

The operators of the polyfunctional building are Oremus estate s.r.o. and Logman a.s. Bratislava. Tenants of the building are pharmacy, eyes optics and doctors with private practice.

As the building is designated for public, it is also built to be wheelchair accessible. To have all the criteria completed, there is a lift behind the entrance.

Within the pharmacy, there is a separate room with lower temperature for storage of medicaments, additives, medical aids, according to procedure´s requirements of Slovak codex This kind of medicine storage is in accordance with law 198/2001 Z.z. The pharmacy is equipped with a closed container for medicaments that weren't used.

On the base of project, requirements of these bodies were :

  • Mesto Trebišov - Mestský úrad, oddelenie výstavby, územného plánovania, ŽP a mestských komunikácií - urbanisticko-architektonické riešenie
  • SPP a.s. - plynofikácia stavby
  • VVS a.s. - vodovodná a kanalizačná prípojka
  • VSE a.s. - elektrická prípojka
Before earthwork started, a responsible worker had assigned the marking of the routes of ingeneer webs under the earth and other barriers. Workers that made earthworks were familiarized with the kind of ingeneer webs, their routes, depth and protected areas.

All the safe directives of the protection of health in work were fulfilled during a construction.